Challenges persist in accelerating Indonesia’s geothermal energy growth

Reading Time: 2 minutes
Journalist IBP

Journalist

Mahinda Arkyasa

Editor

Interview

Entrepreneurs in the geothermal sector have revealed that the growth of installed capacity for geothermal power plants (PLTP) in Indonesia remains sluggish, currently reaching only 40 MW per year. Several challenges are seen as hindrances to the expansion of this clean energy source.

Prijandaru Effendi, the Chairman of the Indonesian Geothermal Association (API), stated that to achieve the target of adding geothermal power plant capacity to 3,355 MW by 2030, an increase of approximately 450 MW per year is required.

Prijandaru noted that the currently installed geothermal capacity stands at 2,378 MW, with an average annual growth of only about 40 MW. Therefore, he emphasized that the growth of geothermal energy is still far from the potential of around 24,000 MW.

“The slow growth is due to various challenges, especially as we are still in the process of finding solutions,” he remarked on September 20, 2023.

He mentioned that some of the challenges that could impede the growth of green energy include the gap between geothermal electricity prices and the project’s economic viability, which may not be attractive to investors.

Furthermore, another challenge is the frequent changes in regulations, leading to uncertainty in the geothermal sector. Hoping to collectively address these challenges in the future.

Ineffective incentives

The Ministry of Energy and Mineral Resources (ESDM) has provided several incentives and facilitations to attract large companies to develop geothermal power plant projects.

“To attract investors, the government has improved regulations related to geothermal energy, including fiscal and non-fiscal incentives, reducing exploration risks through government drilling, preparing financing mechanisms for the exploration stage, and offering new Working Areas (WKPs) and Special Purpose Geothermal Working Areas (WPSPEs),” stated Harris Yahya, Director of Geothermal Energy at the Directorate General of New, Renewable Energy, and Energy Conservation (EBTKE).

However, Fabby Tumiwa, the Executive Director of the Institute for Essential Service Reform (IESR), believes that these incentives are ineffective in attracting investment in the geothermal business. He pointed out that geothermal investment is still seen as high-risk by business players.

“The incentives provided so far have been somewhat ineffective in reducing risks and attracting investment interest,” said Fabby.

He mentioned that the ineffectiveness of these incentives can be observed in the development target for geothermal, which has not met the initial goal of reaching 7,000 MW by 2025.

“We were supposed to reach 7,000 MW by 2025, but it was postponed by the government to 2030 as the target of 7,000 MW,” he explained.

He added that until now, geothermal development has only reached 2,350 MW. This means that the target has not been achieved in line with the expected growth.

“In the last three years, the addition of geothermal power plant capacity has been at most 200-300 MW per year, when we should be growing at a rate of 500-600 MW per year to meet that target,” he clarified.

It is worth noting that Indonesia has the second-largest installed geothermal capacity in the world, with 2,175.7 MWe or 9% utilized for Geothermal Power Plants (PLTP), while the potential capacity stands at 24 GW.

Journalist IBP

Journalist

Mahinda Arkyasa

Editor

 

Interview

SUBSCRIBE NOW
We will provide you with an invoice for your reimbursable expenses.

Free

New to Indonesian market? Read our free articles before subscribing to the premium plan. If you already run your business in Indonesia, make sure to subscribe to the premium subscription so you won’t miss any intelligence & business opportunities.

Premium

$550 USD/Year

or

$45 USD/Month

Cancelation: you can cancel your subscription at any time, by sending us an email inquiry@ibp-media.com

Add keywords to your market watch and receive notification:
Schedule a free consultation with us:

We’ll contact you for confirmation.

FURTHER READING

Coordinating Minister for Maritime Affairs and Investment Luhut Binsar Pandjaitan has revealed that a total of 120 strategic projects related to water and sanitation worth US$9.4 billion are expected to be agreed upon during the 10th World Water Forum that will be held in Bali on May 18-25, 2024.
The shareholders’ meeting of PT Pertamina International Shipping (PIS), a subsidiary of State oil and gas company PT Pertamina, has appointed Muhammad Resa as the company’s Director of Risk Management, with the aim of enabling the company to pursue aggressive growth while maintaining a strong focus on risk management.
PT Pertamina Power Indonesia, also known as Pertamina NRE, has highlighted that the current cost of hydrogen for transportation remains uncompetitive. Hydrogen is mainly used in the transportation sector for specialized fuel cell electric vehicles (FCEVs).
State electricity company PT PLN has completed the construction of the 2 X 55 MegaWatt (MW) Jatigede Hydroelectric Power Plant (PLTA) in Sumedang Regency, West Java.
Several companies have expressed their interest in managing the oil and gas Andaman III Block following the departure of previous operators Repsol and Petronas. The two firms decided not to extend their exploration period, which ended on June 23, 2023.
PT Amman Mineral Nusa Tenggara has reported significant progress in the construction of their copper smelter facility in West Sumbawa, with the mechanical completion slated for May 2024.